Timbertown Review
Read this: Redevelopment Cost Estimates (50.5 KB)
This consultation has concluded. You can still browse the site but the discussion area will no longer accept new comments or votes.
Council is undertaking a full review of Timbertown to establish the parks viability. It is widely acknowledged that Timbertown is in need of major maintenance and capital improvements and it is with this in mind that Administrator Garry Payne has asked for this review to be immediately undertaken.
Over several years the annual Council subsidy to Timbertown has increased, with operating loss in 2008 of over $500,000. A report into Timbertown has identified that due to its aging buildings and infrastructure the park cannot continue operating under its current conditions.
Council is considering either significantly redeveloping the theme park or closing it. Redevelopment costs of the park have been estimated in excess of $15 million which would result in a significantly enhanced tourism facility with added attractions and an entry fee closer to standard market rates. See the libary for further details on estimate and issues.
The information gained from a random telephone survey of 600 residents, as well as community forums in Wauchope, Port Macquarie and Laurieton and this online discussion will help Council to determine the future of Timbertown.
The following links reload the page with different content below.
Sorted by Activity | Date
My ideas for redevelopment of Timbertown
If Timbertown was to be redeveloped to make it a significant and viable tourism facility, what additional activities and experiences do you think should be part of the theme park?
by PMHC Project Coordinator 2:55pm, 14 July 2009 |
916 views |
42 comments
How the community values Timbertown
What do you value most about Timbertown? What effect would it have on the local community and the Hastings if Timbertown was to be closed? Please comment on the social, economic and other impacts you think important.
by PMHC Project Coordinator 2:53pm, 14 July 2009 |
820 views |
17 comments
Considering Funding Sources
Redevelopment of Timbertown has been estimated at a cost of $15 million. Council wants your ideas on meeting these initial redevelopment costs and the potential structure to ensure ongoing financial stability of the park. How should the initial redevelopment costs be funded? How Should Council ensure the ongoing financial stability of Timbertown?
by PMHC Project Coordinator 2:57pm, 14 July 2009 |
588 views |
14 comments



Key Links
Photographs
Frequently Asked Questions
Key Dates
Project Team
Library
Quick Survey